Coldwater Storage Construction Update

This month, we began construction on both our permanent operations building as well as the addition of a 75 megawatt battery storage project

August 18, 2026
Rows of solar panels installed on a grassy hillside under a clear blue sky, with forested hills visible in the distance.

This month, we began construction on both our permanent operations and maintenance building as well as the addition of a 75 megawatt battery storage component to the project.

Meanwhile, we are also preparing to make our first full property tax payment next month, which totals around $1 million for local schools, Branch County, and Coldwater and Ovid Townships.

In this newsletter you will find a general overview of the construction timeline for the energy storage project and resources if you are interested in learning more about how these projects work and the benefits they provide to the regional electric grid.

About Battery Storage

Put simply, battery storage projects store excess electricity during periods of low demand and save that energy for when it is most needed. By discharging the battery, we can not only  reduce costs during peak times, but also help prevent shortages and protect the grid in case of emergency.

At Coldwater, our battery storage component can charge from either the solar project or the grid. This means that on a warm sunny day when we are generating more power than the grid needs, we can save that power for when it is most needed rather than letting it go to waste.

As a 75 megawatt, 4-hour battery, Coldwater Storage will be able to store 300 megawatt-hours of electricity. That's enough electricity to power 10,000 average American homes for an entire day or maintain power to 60,000 homes over a single 4-hour discharge.

Watch the video below to learn more about how Apex's operating battery projects in Texas are enhancing the reliability of the electric grid. For more facts on energy storage, click here.

Construction Timeline - Operations Building & Coldwater Storage

Earlier this month, our Michigan-based construction partner, Barton Malow, began mobilizing for construction of the energy storage project. Work thus far has primarily entailed site preparation (grading, stormwater features, etc.). Here is what to expect in the months ahead:

  • September/October 2026
    • Continued site preparation
    • Access roads
  • November/December 2026
    • Trenching and installation of underground line
  • January-March 2027
    • Delivery of Battery Energy Storage Systems (BESS) and inverters to site in January, followed by placement and installation.
    • Construction of substation expansion to accommodate additional transformer
  • June-July 2027
    • BESS commissioning and inspections
    • Commence commercial operations (Estimated July 2027)

Construction of our operations and maintenance building will occur in parallel to the storage project, and is anticipated to be complete before we commence commercial operations on the energy storage project next summer. Once the building is complete, it will become our permanent home for our solar technicians and equipment. Restoration of the remaining parts of the laydown yard at the corner of Fenn Road and Sanford will follow as we demobilize.

This fall, we will also replant trees in the few screening segments where we have dead or damaged pine trees due to herbicide drift and other factors.

Questions or Feedback

Similar to the solar project construction process, if there are any issues that arise during construction, please fill out the complaint form on our website and we will investigate and get back to you as soon as possible. Our project website is currently under construction as part of a refresh, but the link to the complaint portal remains active on the landing page in the meantime.

Thank you again for your patience and understanding during construction activities - we look forward to completing this process and moving into our new space as soon as possible. In the meantime, please don't hesitate to contact us by phone or e-mail with any additional questions.

Warmly,

The Coldwater Solar Team

Share this post